Madison Update: September 17-October 18

September 17-Airlifting lumber and supplies on a rare clear day

September 18-Demo complete, new deck added along with bathroom bins

September 19-First walls are raised along with the 2000lb carrying beam

October 2-Walls and roof up, starting to shingle

October 2-View from the dining room front door looking towards the future kitchen, crew room and bathrooms

October 3-Bathrooms being closed in

October 9-Dining room and bunk room ridges meet with J.Q. Adams in the background

October 18-Windows installed just in time to keep the snow out

October 18-Construction Crew workers finishing exterior shingling and enjoying the winter weather